ArcelorMittal → Applications → Études de cas – en ligne → Breakwater of the ‘Marina Pez Vela’ | Quepos | Costa Rica
Breakwater of the ‘Marina Pez Vela’ | Quepos | Costa Rica
In 2007 a group of local investors decided to start working on a project that would benefit locals as well as tourists. Marina "Pez Vela" had been planned for years and started to become reality. The 308 slip marina features one of the most sophisticated breakwaters ever built for a recreational marina, providing a safe harbour and hurricane protection. The extra-wide, modern, concrete floating docks, allow safe loading of passengers and equipment, and secure mooring. The first phase of construction includes 100 slips accommodating yachts up to 61 m in length. Being built with an emphasis towards environmental protection, which includes the use of recycled steel and the installation of a water treatment system, the marina will fully meet American and Costa Rican building codes and standards.
The design considered the needs of the boat owners and the necessary infrastructure to host the future landing point. The governing design factor in this case was the standard wave height of 2.5 m. During the first discussions this was assumed as too big, but actual experience proved it was a good assumption.
To achieve adequate shelter for the boats, a strong and reliable breakwater had to be built. Different gravity structures were analysed, including rock dam, rectangular 'double wall' sheet pile cofferdam, concrete caissons and circular cells cofferdam.
The limited availability of aggregates in the area made the rock dam solution very difficult and expensive. At the same time, concrete caissons would have required too much construction time.
Consequently the final choice for the 540 m long breakwater was a circular cell cofferdam with AS 500 straight web steel sheet piles which offers multiple advantages:
- once the crew acquires the necessary training, installation is quick. Time required to finish one cell is only 7-8 working days,
- after the cell is closed and backfilled, the system is auto-stable and can resist wave loads, and support the crane, thus ensuring safety. The temporary template, and later the backfill, stabilizes the structure, hence no tie-back system is needed,
- the use of 'mariner' steel grade according to ASTM A690, with additional alloy content (copper,…), provides higher resistance against corrosion in the splash zone,
- the cell diameters of 12.2 m and 18.6 m offer significant space for development along the top of the wall,
- the flexible structure's performance under seismic loading is good.
The whole project was implemented by a local contractor with the help of an experienced pile driving crew. Additional technical support was provided during the design stage and execution phase by ArcelorMittal's technical department.
After site installation and construction of the first 12 m diameter template, pile installation started with one crew. It became clear to the project owner during the early days itself that the circular cell solution was the correct decision. The rough weather and waves of more than 2.5 m gave the crew a hard time. Even the crane was hit by a wave that overtopped the dam. Nevertheless, execution of the circular cells progressed as planned.
Later on the fabrication of the second template with a diameter of 18 m was completed, and work started on the opposite side of the breakwater with a second crane. The same conditions for the design were imposed - resistance against horizontal impact of the waves and vertical bearing capacity for a 150 t crane.
The backfill of the first cells was brought in from a local sand pit. Shortly after, a dredger was used to draw out sand from within the marina and dump it into the cells. Compaction of the sand fill is done by gravity and is accelerated by vertical drains. In areas with high vertical loads on the cells, additional foundation piles were installed.
After completion of the breakwater in November 2008, prefabricated 'tetrapodes' were placed on the outside of the marina. In a next stage all other shipbuilding facilities, housing and even a waste water treatment plant were built.
Since the design took into account seismic loads, a recent earthquake with a magnitude of 6.4 did not cause any damage to the steel structure.
In the future the marina will give shelter not only to the tourist boats, but also to the local fisherman - a dramatic improvement over the situation that existed before its construction.
Project owner |
Marina Pez Vela | Costa Rica |
Main contractor |
MECO | Costa Rica |
Steel sheet piles |
AS 500-11.0 | ASTM A690 | 7.0 - 15.0 m | I.S. = 3 500 kN/m
AS 500-12.7 | ASTM A690 | 9.0 - 14.3 m | I.S. = 5 500 kN/m |
Quantity |
3 340 t |
First published:
Latest revision: 01/2019
Dernière modification : mars 5, 2019